The history of VMT navigation systems

Let’s experience the milestones in our 30-year development history together…


1994
First field deployment in Zürich

The initial SLS-RV prototype was deployed on a construction site in Zürich for the Gießen-Lyren project for the joint venture “ARGE Abwassersammler”. This marked the first practical application of VMT’s navigation system technology.

Read more

Key aspects:

  • Geodimeter 620 tachymeter
  • Custom interface box
  • ELS laser target
  • Kontron PC with floppy drive

Notably, portions of the software were developed on-site directly within the shaft. This approach allowed for immediate testing and refinement of the system under real-world conditions.

 

Erster Baustelleneinsatz in Zürich

Der erste Prototyp des SLS-RV wurde auf einer Baustelle in Zürich beim Projekt Giessen-Lyren für die ARGE Abwassersammler eingesetzt. Dies war der erste praktische Einsatz der Navigationstechnologie von VMT.

Mehr erfahren

Die Highlights:

  • Geodimeter 620 Tachymeter
  • Kundenspezifische Interface-Box
  • ELS Laser Zieltafel
  • Kontron PC mit Diskettenlaufwerk

Ein Teil der Software wurde vor Ort direkt im Schacht entwickelt. So konnte das System sofort unter realen Bedingungen getestet und angepassst werden.

 

1995
Erstes Projekt mit großem Durchmesser in London
Erstes Projekt mit großem Durchmesser in London

Das erste Tunnelbauprojekt mit großem Durchmesser, bei dem das SLS-T-System zum Einsatz kam, wurde beim Projekt Jubilee Line in London realisiert.

Mehr erfahren

Die Highlights:

  • Navigation für den Tübbingausbau mit dem SLS-T System
  • Drittsoftware ACS-II (Tacs), basierend auf Windows 3.11
  • VMT-Hardware, einschließlich einer kundenspezifischen Schnittstellenbox
  • Umfassender Service, Training und Inbetriebnahme durch VMT

Dieses Projekt unterstreicht die Fähigkeit von VMT, fortschrittliche Navigationssysteme zu integrieren und zu unterstützen, um eine präzise und zuverlässige Leistung in komplexen Tunnelbauumgebungen zu gewährleisten.

 

First large diameter project in London
First large diameter project in London

The first large diameter tunnelling project featuring the SLS-T system was implemented on the Jubilee Line in London.

Read more

Key aspects:

  • Navigation for segmental lining using the SLS-T system
  • Third-party software ACS-II (Tacs) based on Windows 3.11
  • VMT hardware, including a custom interface box
  • Comprehensive service, training, and commissioning provided by VMT

This project underscored VMT’s capability to integrate and support advanced navigation systems, ensuring precise and reliable performance in complex tunnelling environments.

 

1996
VMT-Navigationssystem: Gemeinschaftsentwicklung mit Leica
VMT-Navigationssystem: Gemeinschaftsentwicklung mit Leica

Ein wichtiger Meilenstein in der Navigationsgeschichte von VMT war die gemeinsame Entwicklung eines neuen Tachymeters. Die Partnerschaft zwischen VMT und Leica führte zu einer hochmodernen Lösung, die speziell auf die Anforderungen im Tunnelbau zugeschnitten ist.

Mehr erfahren

Die Highlights:

  • Gemeinsame Entwicklung des Leica TPS 1000 Tachymeters mit GUS 64 Laser
  • Verbindung der Expertise von VMT im Tunnelbau mit der Präzisionsmesstechnik von Leica

Diese Zusammenarbeit spiegelt das Engagement von VMT für Innovation und Partnerschaft wider und hat zur Entwicklung eines leistungsstarken und zuverlässigen Systems geführt, das neue Maßstäbe in der Tunnelnavigation und -vermessung setzt.

 

VMT navigation system: Joint development with Leica
VMT navigation system: Joint development with Leica

A significant milestone in VMT’s navigation history was the collaborative development of a new tachymeter. This partnership between VMT and Leica resulted in a cutting-edge solution tailored for advanced tunnelling applications.

Read more

Key aspects:

  • Joint development of the Leica TPS 1000 tachymeter with GUS 64 laser inside
  • Integration of VMT’s expertise in tunnelling with Leica’s precision measurement technology

This collaboration exemplified VMT’s commitment to innovation and partnership, leading to the creation of a robust and reliable system that has set new standards in tunnelling navigation and measurement.

 

1997
Die ersten Projekte mit Leica TPS 1000

Nach der Entwicklung des TPS 1000 wurde das System erstmals in zwei verschiedenen Projekten erfolgreich eingesetzt und ersetzte das Geodimeter.

Mehr erfahren

Die Highlights:

  • Erstes Tunnelprojekt mit grossem Durchmesser mit dem neuen Tachymeter: Heinenoord, Niederlande
  • Erstes Microtunneling-Projekt mit Leica Tachymeter: Regensburg/Burgweinting, Deutschland

Die Integration des Leica TPS 1000 Tachymeters, das speziell für VMT entwickelt wurde, stellt eine neue Hauptkomponente in unseren Steuerungssystemen dar.

 

Erste voll integrierte SLS-RV in Herrenknecht-TBM

VMT hat mit der Implementierung des ersten voll integrierten SLS-RV-Systems in eine Herrenknecht-TBM in Nordengland einen wichtigen Meilenstein zur Steigerung der Präzision und Effizienz im Tunnelbau erreicht.

Mehr erfahren

Die Highlights:

  • Kombination fortschrittlicher Navigationstechnologien in einem einzigen, durchgängigen System zur Verbesserung der Genauigkeit und der Betriebseffizienz
  • • Verwendung robuster Komponenten und offener Schnittstellen, um langfristige Zuverlässigkeit und Anpassungsfähigkeit an zukünftige Anforderungen zu gewährleisten

Diese Entwicklung verdeutlicht das Engagement von VMT, zukunftsorientierte und hochmoderne Lösungen bereitzustellen, die den wachsenden Anforderungen der Tunnelbauindustrie gerecht werden.

 

Einführung der Schnittstellenbox “Yellowbox“

VMT hat die „Yellowbox“ entwickelt, eine innovative Schnittstellenbox mit Tachymeter-Kabeltrommel, die die Konnektivität und Effizienz im Tunnelbau verbessert.

Mehr erfahren

Die Highlights:

  • Einfacher Anschluss von Tachymetern, vereinfachte Datenübertragung und verbesserte Betriebseffizienz mit der „Yellowbox“
  • Vereinfachte Installation und geringerer Bedarf an aufwendiger Verkabelung, was zu Kosteneinsparungen und einfacherer Wartung führt

Diese Entwicklung unterstreicht das Engagement von VMT, intelligente Lösungen anzubieten, die den sich ändernden Anforderungen der Tunnelbauindustrie gerecht werden.

 

First projects with Leica TPS 1000

Following the development of the TPS 1000, the system was successfully used for the first time in two different projects, replacing the Geodimeter.

Read more

Key aspects:

  • First large diameter tunnelling project with the new tachymeter: Heinenoord, Netherlands
  • First microtunnelling project with the Leica tachymeter: Regensburg/Burgweinting, Germany

The integration of the Leica TPS 1000 tachymeter, specifically developed for VMT, represented a new main component in our control systems.